Quiz: Project Management and COCOMO: questions with answers
10 questions, each with the answer and a short explanation.
Take the timed quiz + get a certificate →- Q1. In basic COCOMO, which mode suits a small, experienced team building a familiar application?
- Q2. Optimistic 3, most likely 6, pessimistic 15 days. What is the PERT expected time?
- Q3. UFP = 200 and ΣFi = 35. What is FP?
- Q4. The critical path in a task network is the:
- Q5. Effort is 120 person-months and development time is 12 months. Average team size?
- Q6. A system has 5 EI, 4 EO, 3 EQ, 2 ILF and 1 EIF, all of average complexity. What is the UFP?
- Q7. What is the range of the value adjustment factor (0.65 + 0.01 × ΣFi) in function point analysis?
- Q8. An organic project has 10 KLOC. Using E = 2.4 × KLOC^1.05, the effort is about:
- Q9. Task A takes 3 days. B (2 days) and C (5 days) both start after A. D (1 day) starts after both B and C finish. How much slack does B have?
- Q10. A risk has a 20% probability and would cost ₹5 lakh if it happens. What is its risk exposure?