Quiz: Project Management and COCOMO · Question 2 of 10

Optimistic 3, most likely 6, pessimistic 15 days. What is the PERT expected time?

Optimistic 3, most likely 6, pessimistic 15 days. What is the PERT expected time?

  1. A.6
  2. B.7
  3. C.8
  4. D.8.5
Answer & explanation

Correct answer: 7

(3 + 4×6 + 15) ÷ 6 = 42 ÷ 6 = 7 days.