Optimistic 3, most likely 6, pessimistic 15 days. What is the PERT expected time?
Optimistic 3, most likely 6, pessimistic 15 days. What is the PERT expected time?
- A.6
- B.7
- C.8
- D.8.5
Answer & explanation
Correct answer: 7
(3 + 4×6 + 15) ÷ 6 = 42 ÷ 6 = 7 days.