A system has 5 EI, 4 EO, 3 EQ, 2 ILF and 1 EIF, all of average complexity. What is the UFP?

A system has 5 EI, 4 EO, 3 EQ, 2 ILF and 1 EIF, all of average complexity. What is the UFP?

  1. A.15
  2. B.75
  3. C.79
  4. D.95
Answer & explanation

Correct answer: 79

5×4 + 4×5 + 3×4 + 2×10 + 1×7 = 20 + 20 + 12 + 20 + 7 = 79.