Quiz: Project Management and COCOMO · Question 5 of 10
Effort is 120 person-months and development time is 12 months. Average team size?
Effort is 120 person-months and development time is 12 months. Average team size?
- A.12
- B.10
- C.1440
- D.132
Answer & explanation
Correct answer: 10
Staff = E ÷ D = 120 ÷ 12 = 10.