The critical path in a task network is the:

The critical path in a task network is the:

  1. A.Shortest path
  2. B.Longest path
  3. C.Path with the most tasks
  4. D.Path with slack
Answer & explanation

Correct answer: Longest path

The longest path decides the minimum project duration.