Task A takes 3 days. B (2 days) and C (5 days) both start after A. D (1 day) starts after both B and C finish. How much…
Task A takes 3 days. B (2 days) and C (5 days) both start after A. D (1 day) starts after both B and C finish. How much slack does B have?
- A.0 days
- B.2 days
- C.3 days
- D.5 days
Answer & explanation
Correct answer: 3 days
Critical path A→C→D = 9 days; A→B→D = 6 days; slack of B = 9 − 6 = 3.