Task A takes 3 days. B (2 days) and C (5 days) both start after A. D (1 day) starts after both B and C finish. How much…

Task A takes 3 days. B (2 days) and C (5 days) both start after A. D (1 day) starts after both B and C finish. How much slack does B have?

  1. A.0 days
  2. B.2 days
  3. C.3 days
  4. D.5 days
Answer & explanation

Correct answer: 3 days

Critical path A→C→D = 9 days; A→B→D = 6 days; slack of B = 9 − 6 = 3.