Quiz: Time and Work · Question 9 of 15

12 men or 18 women can do a job in 14 days. How many days will 8 men and 16 women take?

12 men or 18 women can do a job in 14 days. How many days will 8 men and 16 women take?

  1. A.10 days
  2. B.12 days
  3. C.9 days
  4. D.8 days
Answer & explanation

Correct answer: 9 days

12 men = 18 women, so 1 man = 1.5 women. 8 men + 16 women = 12 + 16 = 28 women. Work = 18 × 14 = 252 woman-days. 252 ÷ 28 = 9 days.