20 men working 8 hours a day finish a job in 15 days. How many days will 24 men working 10 hours a day take?

20 men working 8 hours a day finish a job in 15 days. How many days will 24 men working 10 hours a day take?

  1. A.12
  2. B.8
  3. C.10
  4. D.9
Answer & explanation

Correct answer: 10

M₁H₁D₁ = M₂H₂D₂: 20 × 8 × 15 = 24 × 10 × D, so D = 2,400 ÷ 240 = 10.