Quiz: Time and Work · Question 13 of 15
20 men working 8 hours a day finish a job in 15 days. How many days will 24 men working 10 hours a day take?
20 men working 8 hours a day finish a job in 15 days. How many days will 24 men working 10 hours a day take?
- A.12
- B.8
- C.10
- D.9
Answer & explanation
Correct answer: 10
M₁H₁D₁ = M₂H₂D₂: 20 × 8 × 15 = 24 × 10 × D, so D = 2,400 ÷ 240 = 10.