Quiz: Requirements and SRS · Question 8 of 10

In which step of requirements engineering are conflicts, duplicates and ambiguities removed?

In which step of requirements engineering are conflicts, duplicates and ambiguities removed?

  1. A.Elicitation
  2. B.Analysis
  3. C.Validation
  4. D.Feasibility study
Answer & explanation

Correct answer: Analysis

Elicitation gathers; analysis cleans and prioritises; validation confirms with the customer.