At t = 9 in the HRRN example, why was C chosen over E?

At t = 9 in the HRRN example, why was C chosen over E?

  1. A.C had waited 5 units, so its ratio (9/4 = 2.25) was higher than E's (3/2 = 1.5)
  2. B.C arrived later than E
  3. C.C had the shortest burst
  4. D.HRRN always picks in arrival order
Answer & explanation

Correct answer: C had waited 5 units, so its ratio (9/4 = 2.25) was higher than E's (3/2 = 1.5)

HRRN rewards waiting; E's short burst was not enough to beat C's longer wait.