Quiz: Agile and Scrum · Question 9 of 10
Why do teams estimate in story points instead of hours?
Why do teams estimate in story points instead of hours?
- A.Points measure relative effort, which people estimate more reliably than exact hours
- B.Points are always equal to 8 hours
- C.Hours cannot be written in a backlog
- D.Story points are required by law
Answer & explanation
Correct answer: Points measure relative effort, which people estimate more reliably than exact hours
Comparing "this is about twice as big as that" is easier than predicting hours.