Quiz: Agile and Scrum · Question 3 of 10
A team's last sprints completed 18, 22 and 20 points. About how many sprints will a 100-point backlog take?
A team's last sprints completed 18, 22 and 20 points. About how many sprints will a 100-point backlog take?
- A.4
- B.5
- C.6
- D.10
Answer & explanation
Correct answer: 5
Average velocity = 60 ÷ 3 = 20, so 100 ÷ 20 = 5 sprints.