# Software Project Management — LOC, Function Points, COCOMO, CPM and Risk

Source: https://skills101.in/learn/software-engineering/software-project-management-cocomo — Skills101 free tutorial (Software Engineering). Updated 2026-11-09.

"How long will it take and how many people do we need?" Every project manager must answer this — and every university exam has a COCOMO or function-point numerical.

## 1. Measuring size

**LOC / KLOC** (lines of code / thousands of lines). Easy to count *after* coding, but depends on language and style and is hard to know early.

**Function points (FP)** measure size from the **functionality** users see, independent of language.

### Function point calculation

Count five components and multiply by weights (average complexity shown):

| Component | Weight (avg) |
|---|---|
| External Inputs (EI) | 4 |
| External Outputs (EO) | 5 |
| External Inquiries (EQ) | 4 |
| Internal Logical Files (ILF) | 10 |
| External Interface Files (EIF) | 7 |

(Simple and complex weights also exist: EI 3/4/6, EO 4/5/7, EQ 3/4/6, ILF 7/10/15, EIF 5/7/10.)

**Example:** 10 EI, 8 EO, 6 EQ, 4 ILF, 2 EIF, all average.

UFP (unadjusted) = 10×4 + 8×5 + 6×4 + 4×10 + 2×7 = 40 + 40 + 24 + 40 + 14 = **158**

Then rate 14 general system characteristics from 0 to 5; their total is ΣFi. Say ΣFi = 42.

**FP = UFP × (0.65 + 0.01 × ΣFi)** = 158 × (0.65 + 0.42) = 158 × 1.07 = **169.06**

(The multiplier — the value adjustment factor — ranges from 0.65 to 1.35.)

## 2. Basic COCOMO (Boehm, 1981)

**Effort E = a × (KLOC)^b** person-months
**Development time D = c × (E)^d** months
**Average staff = E ÷ D**

| Mode | Project type | a | b | c | d |
|---|---|---|---|---|---|
| Organic | small team, familiar, flexible (payroll) | 2.4 | 1.05 | 2.5 | 0.38 |
| Semi-detached | medium, mixed experience (a DBMS) | 3.0 | 1.12 | 2.5 | 0.35 |
| Embedded | tight hardware/real-time constraints (avionics) | 3.6 | 1.20 | 2.5 | 0.32 |

### Solved example

An organic project of 32 KLOC.

- E = 2.4 × 32^1.05 = **91.3 person-months**
- D = 2.5 × 91.3^0.38 = **13.9 months**
- Staff = 91.3 ÷ 13.9 ≈ **6.6, about 7 people**

The same 32 KLOC as **embedded**: E = 3.6 × 32^1.20 = **230.4 PM**, D = 14.3 months, about 16 people. Harder constraints mean much more effort for the same size.

**Intermediate COCOMO** multiplies effort by an **EAF** (effort adjustment factor) from 15 cost drivers (reliability, team capability, tools…). **Detailed COCOMO** applies drivers per phase. **COCOMO II** updates the model for modern, reuse-heavy development.

## 3. Scheduling

- **Work breakdown structure (WBS)** — split the project into small tasks.
- **Gantt chart** — tasks as bars on a calendar; shows overlaps and progress.
- **PERT** — for uncertain durations: expected time **te = (o + 4m + p) ÷ 6** (optimistic, most likely, pessimistic). With o = 2, m = 4, p = 12: te = (2 + 16 + 12) ÷ 6 = **5 days**.
- **CPM (critical path method)** — the longest path through the task network decides the project length.

![Task network: A of 3 days leads to B of 2 days and C of 4 days, both lead to D of 2 days; the critical path A, C, D takes 9 days](https://skills101.in/learn-img/software-engineering/cpm.svg)

Paths: A→B→D = 3 + 2 + 2 = 7 days; A→C→D = 3 + 4 + 2 = **9 days** (critical). Any delay in A, C or D delays the project. B has **slack (float)** of 9 − 7 = 2 days.

## 4. Risk management

1. **Identify** risks — project (staff leaves, budget cut), technical (new framework), business (market changes).
2. **Analyse** — probability × impact = risk exposure.
3. **Plan** — avoid, reduce (mitigate), transfer, or accept.
4. **Monitor** throughout the project.

Example: risk "key developer may leave" (probability 30%, impact high) → mitigation: pair programming and documentation so knowledge is shared.

## Common mistakes

- Using the organic constants for an embedded project.
- Forgetting COCOMO's input is in **KLOC** (32,000 lines = 32).
- Choosing the *shortest* path as the critical path — it's the **longest**.

## Quick recap

- Size: LOC or function points (FP = UFP × (0.65 + 0.01 ΣFi)).
- Basic COCOMO: E = a(KLOC)^b, D = c(E)^d, staff = E ÷ D; organic, semi-detached, embedded.
- PERT te = (o + 4m + p) ÷ 6; critical path = longest path; slack = spare time.
- Risks: identify, analyse, plan, monitor.